Phase 3

Edison Elementary

NOTE:The dates are educated estimates based prior documentation and will be refined after the structural assessment and design work for the site as well as completion of prior phases. These timetables were prepared in March, 2004.

Structural Assessment

  • Estimated Start Date: April, 04 Estimated Finish Date: May, 04
  • Design Time LPA Design Process

  • Estimated Start Date: May, 05 Estimated Finish Date: August, 05
  • DSA Approvals

  • Estimated Start Date: August, 05 Estimated Finish Date: November, 05
  • Bidding

  • Estimated Start Date: November, 05 Estimated Finish Date: December, 05
  • Design Interim Housing

  • Estimated Start Date: July, 05 Estimated Finish Date: September, 05
  • Utilities for Interim Housing

  • Estimated Start Date: September, 05 Estimated Finish Date: September, 05
  • Procure Interim Housing

  • Estimated Start Date: September, 05 Estimated Finish Date: November, 05
  • Install Interim Housing

  • Estimated Start Date: November, 05 Estimated Finish Date: November, 05
  • Install Alarm Devies

  • Estimated Start Date: November, 05 Estimated Finish Date: November, 05
  • Patch Utilities/Ramps

  • Estimated Start Date: November, 05 Estimated Finish Date: November, 05
  • Construction

  • Estimated Start Date: December, 05 Estimated Finish Date: March, 06
  • Back to Construction Home Page

    Back to Measure C Home Page

    Send mail to mikemcmahonausd@yahoo.com with questions or comments about this web site.
    Last modified: March 23, 2004

    Disclaimer: This website is the sole responsibility of Mike McMahon. It does not represent any official opinions, statement of facts or positions of the Alameda Unified School District. Its sole purpose is to disseminate information to interested individuals in the Alameda community.